- Floor refinishing. It starts tomorrow!
- Interior painting. We're painting everything - old and new, walls, doors, trim. Starts after the floor stain and first poly coat is down.
- Staircase finalized. The handrails, newel posts and balusters are in.
- Gutters. They are an installation-in-progress.
- Vanity tops. I head to a stone place tomorrow to look at our options.
- Cabinet hardware. Just chose that last night.
- Front door. Just chose that last night too. And apparently without a moment to spare: the builder says it may take up to six weeks to get it!
- Bathroom fixtures come in. Vanities, faucets, tub, toilets, etc.
- All sorts of tiny little trimwork jobs finalized, especially where old and new rooms have come together.
- Shower glass enclosures need to be chosen.
- We have to choose the other bathroom fixtures...mirrors, towel bars, etc.
- WE MUST CHOOSE OUR LIGHTS. *sigh*
- Railings on the porch.
- Porch steps and path laid in.
- Ack - the door knobs!
- Outlets and switches of course. Right now they're all just holes with with metal boxes and wires poking out.
- Closet 'system' figured out. Think, 'least expensive chic'.
- We have to decide if we're staining the front porch or not.
- Doorbell dilemma. By that I mean: we've never had a working doorbell. Just last week (known in builder terms as, I'm just guessing here, 'now you mention it hour'), the mister asked if it was possible to get a working one.
- Leak mystery. I'm going to be breezy here, because it's how I'm coping. About 10 days ago we were in the house and I heard water running in the pipes. We checked everything inside and out and couldn't find a thing. The builder came over and he couldn't find anything. He shut off the water valve and it stopped. Plumber is scheduled for a visit. Please think cheap-fix thoughts.
- Choose the bedroom carpets. The mister is all giddy about this task. And no, I'm not joking!
We haven't scheduled a move-out date just yet, but we're preparing to commence to begin to think about it!